top of page
Search
  • ltretiak

End of March 2024 Construction Update

The project is progressing as anticipated and we are currently 9% complete!


Activities for this week into next week will include:

  • Continuing bulk excavation of the site and hauling the material off-site.

  • At the end of this week, they will begin to install concrete forms and rebar for the foundation footings.

  • Concrete placement will be scheduled for the week of 3/25.

 

Looking into next month, the main activities that will take place in April are the installation of the foundation and footing concrete and the installation of the underground utilities, plumbing and electrical, all within the building footprint.


Please contact us if you have any questions about the construction or the building. My direct line is #978-540-2471. -Liz Tretiak, Director of Elder and Human Services




23 views0 comments

Recent Posts

See All
bottom of page